Current Projects
This page still under construction.

Walden Galleria
Cheektowaga, NY

Recent upgrade of rooftop HVAC units at Walden Galleria, Cheektowaga, NY for Pyramid Corp.
   
New rooftop units are ultra high efficiency with gas heat to replace electric heat units.
   
Tri-R Mechanical Services was able to obtain financial incentives for high efficiency upgrades from NYSERDA.
   
The helicopter removal and replacement of the 15 HVAC units in this phase was completed in 1 hour 15 minutes with a crew of 9.
   
The HVAC units in this phase ranged in size from 15 to 18 tons.
   
The mall is approximately one-half mile from Buffalo International Airport and directly in its flight path. All air traffic was diverted to another runway during this operation.
   
Our crews replace about 200 HVAC units like this a year.
   
 
   
 
   
 
   
 
   
 
   
 
   
 
   
Bertrand Chaffee Hospital - Springville ,NY
Old air condition being removed.
   
A custom fabricated adaper is being set on the roof.
   
A new 100 ton A/C is being rigged.
   
New 100 ton A/C being set in position.
 
Eastern Niagara Hospital
A new gas regulator assembly being built at Eastern Niagara Hospital in Newfane
   
New pumping station for the Eastern Niagara Hospital Expansion
   
New duct work at Eastern Niagara Hospital
 
International Fiber Corporation
An elevated pallet press
   
 
   
 
   
An adjustable dust collector
   
 
   
 
   
Safety Stairs
   
 
   
Eastern Hills Mall
Preparation for replacing 16 rooftop HVAC units for the Thurman Thomas / New Era Sports Facility
   
 
   
 
   
 
   
 
   
Several rooftop units were removed in a tight spot
   
 
   
 
 
Old equipment is taken away for proper disposal
   
 
 
New rooftop units are lifted into place for final connection
   
 
 
The last few units are removed and set.
   
 
   
All 16 units were removed and new ones set in
aprox. 8 hrs over 2 days.
 
Process Air Drier/Separator for
Luvata (formerly American Brass)
This system was conceived, designed, and built by Tri-R Mechanical
   
 
   
 
   
The 2 large tanks separate impurities before reaching the dessicant
   
 
   
Upon completion in our shop, only power and final pipe connections are required at the plant
   
 
   
 
   
 
   
International Fiber Corp.
North Tonawanda, NY
Various exhaust and material transfer ducts installed at International Fiber Corp.
   
 
   
 
   
 
   
J. Mills Distributing
Orchard Park, NY
Installation of New Refrigerated Warehouse at J. Mills Distributing
   
Installation of New Refrigerated Warehouse at J. Mills Distributing
   
Installation of New Refrigerated Warehouse at J. Mills Distributing
   
Installation of New Refrigerated Warehouse at J. Mills Distributing
   
Installation of New Refrigerated Warehouse at J. Mills Distributing
 
Regenerative Thermal Oxydiser (RTO) installed on presses at Bison Bag Company
Lockport, NY
 
RTO duct entering building
   
RTO pollution control unit
   
Press fume capture hood
   
Custom fume capture hood
   
V.O.C. capture duct
   
Automatic exhaust bypass damper
   
V.O.C. exhaust duct through facility
   
Upgrade gas service to high pressure
   
V.O.C. duct to RTO
   

Rosa's Superstore
Sheridan & Eggert

This store is being built with the management team at Telfair Construction Management.

The HVAC system includes 6 Trane High Efficiency rooftop units linked together by a Trane Tracker Energy Management system. The gas piping ranges from 3" welded to 1/2" threaded black pipe.

 

 

 

Pioneer Credit Management
Perry, New York

Our solid relationship with LBM Construction helped us to secure this project. HVAC consists of 13 York rooftop units linked together by Wattmaster VAV Complete Building Management system.

The Server, Data Processing, and Telecommunications equipment room is controlled by a Liebert Environmental System.

 

   

Electrosynthesis
Lancaster, New York

This multi-million dollar expansion and retrofit is being supervised by Paragon Northeast Construction. Our part of the project includes state of the art air flow control for their Scientific Test Chambers as well as several AAON custom made rooftop HVAC units, and an assortment of explosion proof environmental devices through the facilities.

 

   

OTB
Clinton Street, Buffalo New York

Renovation of HVAC systems and enlargement of their county approved smoking facility.

 

   

Medical Center
Southgate Plaza

This 16,000 sq. ft. comprehensive medical treatment facility is a design build project in cooperation with the Southgate Plaza management Team.

 

   

Bob Weaver Motorsports
Wheatfield, New York

This project includes all new HVAC for the area's newest Yamaha and Polaris Motorsports dealer.

 

   

NOCO

We are now involved with the renovation of several existing NOCO Express stores

 

   

Pottery Barn Kids
Walden Galleria Mall

On this project we are a sub contractor to Pacific Construction of Los Angeles California. The scope of the work involves the demolition of existing HVAC systems and 5 new rooftop HVAC systems tied into the mall's Central Energy Management system.


   

Rosa's Warehouse
Union Road

This addition to their existing warehouse is being heated by a single Cambridge Direct Fired Make Up Air unit. All heated air comes from outside the building for maximum efficiency.

 
 
[Current Jobs] [Customers] [Service Area] [Our History] [Contact Us]
[Testimonials] [Our Services] [Tips & Tricks] [Manufacturers] [Safety]
[Completed Jobs] [Planned Maintenance] [Home Page]
[Employment]
z
   

z
© Copyright 2002-2005 Tri-R Mechanical. All Rights Reserved. All trademarks not owned by Tri-R Mechanical are the property of their respective owners. Prices and availability of products are subject to change without notice. Product descriptions, pictures, and availability are provided with intent of accuracy; however, Tri-R Mechanical is not liable for errors, omissions, or misrepresentations.